Plants you can name, dated, with the salt they produce
These zero liquid discharge projects each carry a location, a capacity, the by-product recovered and the start year. Where one is still being built, it says so.
What these zero liquid discharge projects show
A reference list is only worth something if it can be checked. Each card gives the plant, the place, the flow, the salt produced and the year it started.
Filter by industry to find the water closest to yours, or by delivery model to see how we were contracted.
This is a selection rather than the full record. JINGYU has delivered more than 140 water treatment projects, 45 of them integrated zero liquid discharge systems.
Zero liquid discharge projects, by industry and contract
Filter by industry
Filter by delivery model
Showing all 24 projects
Yitai Fine Chemicals, 1.2 Mt/a
Ordos, Inner Mongolia
- Scale
- Wastewater I 28,800 m³/d · Wastewater II 43,200 m³/d · brine ZLD 13,440 m³/d @ TDS 10 g/L
- Recovered
- Reuse water 43,200 m³/d @ TDS 0.5 g/L · NaCl 20 kt/a · Na₂SO₄ 33 kt/a · salt recovery ≥98%
- Timeline
- Built 2015–2017 · Operating since 2018
Over eight years of continuous, stable operation. China's first ultra-large coal-to-liquids complex certified by the NDRC.
Yitai CTL, 160 kt/a
Ordos, Inner Mongolia
- Scale
- Brine ZLD 1,440 m³/d · evaporation and crystallization 384 m³/d
- Recovered
- Sodium chloride and sodium sulfate, crystallized separately
- Timeline
- Built 2019 · Operating since 2021
China's first indirect coal liquefaction demonstration project. Also the first industrial use of our thermal salt separation route.
Yitai Ili Energy CTL, 1 Mt/a
Ili, Xinjiang
- Scale
- Wastewater plant 26,400 m³/d · reuse plant 40,800 m³/d · ZLD unit 1,920 m³/d
- Recovered
- Reuse water 40,800 m³/d @ TDS 0.2 g/L · NaCl 49 kt/a · Na₂SO₄ 7 kt/a
- Timeline
- Started 2025
The largest contract JINGYU has signed to date.
Huineng Coal-to-Gas, 1.6 bcm/a
Ordos, Inner Mongolia
- Scale
- High-salinity concentration and salt separation ZLD, phase I revamp and phase II
- Recovered
- Separated salts from high-salinity brine
- Timeline
- Built 2018 & 2020 · Operating since 2020 and 2023
China's first coal-water-slurry gasification to natural gas complex. Its phase II gasifier is the largest single unit of its kind anywhere.
Ningxia Baofeng, olefins and methanol
Lingwu, Ningxia
- Scale
- Brine ZLD 3,600 m³/d · evaporation and crystallization 1,248 m³/d
- Recovered
- Crystallized industrial salt from the brine ZLD system
- Timeline
- Built 2019 · Operating since 2022
Baofeng is the world's largest coal-to-olefins producer. JINGYU won its Outstanding Supplier Award for this project.
Yidong Donghua Methanol, 600 kt/a
Ordos, Inner Mongolia
- Scale
- 50 m³/h · evaporation 15 t/h · feed TDS 20,000, hardness 2,000, COD 200, SiO₂ 100
- Recovered
- NaCl and Na₂SO₄ as finished products
- Timeline
- Built 2019 · Operating since 2022
Full recovery of a high-salinity stream, to meet national discharge requirements.
Shanxi Minguang Coking, 1.56 Mt/a
Linfen, Shanxi
- Scale
- Reclaimed water 200 m³/h · NF salt separation 50 m³/h · crystallization 16 m³/h
- Recovered
- NaCl 8 m³/h · Na₂SO₄ 8 m³/h
- Timeline
- Built 2023 · Operating since 2024
A coking upgrade programme with ZLD built into the water system from the start.
Shanxi Coking, brine salt recovery
Linfen, Shanxi
- Scale
- Brine ZLD 4,800 m³/d
- Recovered
- Industrial salt recovered from coking wastewater
- Timeline
- Built 2021 · Operating since 2022
China's first coking wastewater ZLD project. Promoted as a model case by the Shanxi Ecology and Environment Department and the China Coking Industry Association.
Lanhua Coal Chemical, energy and environmental upgrade
Jincheng, Shanxi
- Scale
- Wastewater 4,200 m³/d · reclaimed water 15,000 m³/d · ZLD 4,800 m³/d
- Recovered
- Reuse water 15,000 m³/d @ TDS 0.5 g/L · NaCl 2.3 kt/a · Na₂SO₄ 15.2 kt/a
- Timeline
- Started 2025
A twenty-year build-own-operate contract covering the whole plant water system.
Hongqinghe Mine Water (Yitai Guanglian)
Ordos, Inner Mongolia
- Scale
- 14,400 m³/d
- Recovered
- Reuse water and recovered salt
- Timeline
- Operating since 2020
China's first mine water zero liquid discharge project, on the edge of the Mu Us desert. Owned and operated by JINGYU.
Baijiahaizi Mine Water and Sewage
Wushen Banner, Ordos
- Scale
- 3,000 m³/h · evaporation feed 100 m³/h · feed TDS 5,100, hardness 1,333, COD 20, SiO₂ 10
- Recovered
- Sodium sulfate · mixed salt below 10%
- Timeline
- Built 2022 · Operating since 2023
The largest mine water project by design capacity we have delivered.
Tangjiahui Mine Water
Tangjiahui Mine, Ordos
- Scale
- Underground pretreatment 600 m³/h · advanced treatment 560 m³/h
- Recovered
- NaCl and Na₂SO₄ crystallized on site
- Timeline
- Built 2023 · Operating since 2025
Design, procurement, construction and operation under one contract.
Sunjiacha Longhua Mine Drainage
Shenmu, Shaanxi
- Scale
- 60 m³/h · evaporation feed 30 m³/h
- Recovered
- Sodium chloride and sodium sulfate, co-produced
- Timeline
- Built 2023 · Operating since 2024
Silica removal, sand filtration and ultrafiltration, high-pressure RO, then combined salt and nitrate crystallization.
Huaneng Hetaoyu Coal Mine Water Stations
Zhengning, Gansu
- Scale
- Three stations: mine drainage, industrial and domestic wastewater
- Recovered
- Compliant discharge and reuse
- Timeline
- From 2024 · Contract to 2027
Full outsourced operation. Equipment, chemicals, water quality, sludge and hazardous waste, staffing and compliance.
Jinchuan Group, Nickel and Cobalt Smelting
Jinchang, Gansu
- Scale
- 4,000 m³/d @ TDS 180 g/L
- Recovered
- NaCl 130 kt/a @ ≥98.5% · Na₂SO₄ 150 kt/a @ ≥99% · salt recovery 99%
- Timeline
- Built 2025 · Operating since 2025
Zero liquid discharge for the world's second largest nickel producer. The highest by-product salt output of any JINGYU project.
Zhongtian Green Steel, Central Water Plant
Nantong, Jiangsu
- Scale
- Brine salt separation 145 m³/h · evaporation and crystallization 18 m³/h
- Recovered
- NaCl 18 m³/h crystallized
- Timeline
- Built 2020 · Operating since 2022
Complete supply of the salt separation and crystallization systems, with process and detailed engineering.
Dongming Petrochemical Jieyuan, Phase II
Heze, Shandong
- Scale
- 4,520 m³/d @ TDS 28 g/L
- Recovered
- NaCl 14.7 kt/a @ ≥98.5% · Na₂SO₄ 28.2 kt/a @ ≥97%
- Timeline
- Built 2021 · Operating since 2023
China's first salt separation ZLD project in the petrochemical industry. Process package plus core equipment supply.
PetroChina Dushanzi Tarim Ethylene, 1.2 Mt/a
Bayingolin, Xinjiang
- Scale
- 2,020 m³/d @ TDS 84 g/L
- Recovered
- Recovered water and crystallized salt
- Timeline
- Started 2024 · In commissioning
Phase II zero liquid discharge for one of China's largest ethylene complexes.
Linggu Chemical, ammonia and urea
Yixing, Jiangsu
- Scale
- Brine ZLD 11,280 m³/d · evaporation and crystallization 204 m³/d
- Recovered
- Reuse water 11,280 m³/d @ TDS 0.5 g/L · NaCl 8.8 kt/a @ ≥97.5% · Na₂SO₄ 1.3 kt/a @ ≥99%
- Timeline
- Built 2020 · Operating since 2022
The first full-scale ZLD plant to run successfully in China's fertilizer industry, verified by an industry authority.
Luoyang Jianlong Micronano, molecular sieve park
Luoyang, Henan
- Scale
- 12,000 m³/d
- Recovered
- NaCl 4,300 t/a · KCl 1,700 t/a · K₂SO₄ 11,000 t/a · Na₂SO₄ 20,000 t/a
- Timeline
- Built 2021 · Operating since 2022
China's first ZLD project in molecular sieve materials. The widest range of by-product salts we have produced.
Anhui Huaibei Chemical Base
Huaibei, Anhui
- Scale
- ZLD within an integrated chemical park water system
- Recovered
- NaCl 25 kt/a · Na₂SO₄ 26 kt/a
- Timeline
- Operating
Named a 2023 Typical Case for industrial park water management by China's Ministry of Ecology and Environment.
Mengsu Economic Development Zone (serving LONGi)
Ordos, Inner Mongolia
- Scale
- 18,408 m³/d
- Recovered
- NaCl 42 kt/a @ ≥98.5% · salt recovery 95%
- Timeline
- Operating
The largest photovoltaic wastewater zero liquid discharge plant in the world.
Yinchuan Suyin Industrial Park, water reuse
Yinchuan, Ningxia
- Scale
- 1,050 m³/h, expanding to 25,000 m³/d · feed TDS 1,800, Ca 120, Mg 70, COD 50, SiO₂ 30
- Recovered
- Na₂SO₄ 5 m³/h · NaCl 6.5 m³/h
- Timeline
- Started 2023 · Startup 2025
Ultrafiltration, two-pass reverse osmosis and MVR crystallization. It covers about half the park's industrial water demand, saving over 500,000 tonnes a year.
Shanghai Waste-to-Energy Fly Ash Recovery
Shanghai
- Scale
- 800 t/d, 400 t/d, 300 t/d ×3, 150 t/d ×2, across seven sites
- Recovered
- NaCl 200 t/d @ ≥98.5% · KCl 60 t/d @ ≥93% · condensate below 1,000 mg/L
- Timeline
- Started 2026
Aimed at near-zero landfilling of Shanghai's incineration fly ash. A strategic move to free land for the city's future.
Frequently asked questions
How many zero liquid discharge projects has JINGYU delivered?
More than 140 water treatment projects in total, including 45 integrated zero liquid discharge systems. Eighteen of those are operated by JINGYU under long-term contracts. The projects listed here are a representative selection, not the full record.
Are these plants actually running?
Each card carries a status. Operating means the plant is in commercial service, with the start year given. In commissioning and Under construction mean exactly that. We would rather show a project honestly than round it up.
Can I see the full data for a project?
Yes. Tell us which project interests you and we will provide a full case study. That covers feed water analysis, process configuration, guarantees and operating results, subject to the client's confidentiality terms.
What contract models are represented here?
EPC, EPC plus operation, EPCM plus operation, process package and equipment supply, BOO and BOT, and standalone O&M. Filter by delivery model to see which project used which.
Which project is closest to my water?
Filter by industry first, then read the feed characteristics on each card. If nothing matches closely, that is normal. Send your analysis and we will name the nearest technical reference.
Are any of these outside China?
The projects listed here are in China, where the hardest industrial water in the world is currently treated at scale. Our International Business Division was established in 2025 to bring the same capability to clients abroad.
Ask about the project closest to your water
Start here
Tell us which plant here looks closest to your situation, or send your own analysis. We will come back with the reference that actually matches.
Useful to include
- Your industry and process
- Flow rate and TDS
- Ion balance, COD and hardness
- Discharge limit or reuse target
- Which contract model you prefer
Contact us directly